top of page

Project 07 -
Rockhampton Relocation, Stage 1

Client: APA Group

Location: Rockhampton

Project included:

  • Relocation of Steel and PE network comprising approximately 815m of DN100 API 5L X52 PSL2

  • Open trench road crossings, HDD crossings, Open excavation and lay, night works

  • New DRS and associated connecting pipework and abandonment of the existing DRS

  • Approximately 165m of DN160HDPE for connection between DRS and existing HDPE main

  • Approximately 301m of DN110HDPE constructed to relocate the existing main

  • DN200HDPE sleeve and pullback of the DN110HDPE.

Share

  • Facebook
  • Twitter
  • LinkedIn
  • Instagram
P1346 APA Rockhampton Relocate St1-1.JPG