Liverpool Freight Line Duplication – ARTC

Jemena Asset Management - May to July 2012

The scope of the works for this project was to relocate two secondary pressure natural gas pipelines, test, commission the new sections and decommissions the redundant sections.

Relocation of 2 secondary pressure natural gas pipelines with new DN150 Steel secondary pressure gas mains within the rail at Mill Park Casula. The total pipeline lengths for the two sections were approx. 500 meters, each section was carried out as individual mains and was constructed from a connection point on the existing pipelines.

De-commissioning works pictured below

 

  